Key Facts

  • Client: Midlothian Council
  • Conditions of contract: ICE 5th Edition
  • Contract value: £110,000
  • Duration of works: Completion September 2009 (10 weeks)

Download the case study

Roads & Bridges

Temple Bridge Reconstruction

Temple Bridge carries the C50 Temple Road over the River South Esk which is off the B6372 road, 4km south west of Gorebridge in Midlothian

The project involved the demolition and replacement of the existing deck superstructure which comprised of a reinforced concrete deck sitting on 6 encased steel beams, supported on mass concrete abutments.

The new deck construction consisted of precast, pre-stressed concrete bridge beams and parapet upstands, with an in-situ concrete deck infill. The new deck is supported on in-situ reinforced concrete bearing shelves, cast on the existing concrete abutments.

The overall length of the deck is some 9.5m, with a clear span of 7.6m and overall width of 5.85m.

In addition the work also involves waterproofing, steel parapets, surfacing, kerbing, drainage and localised concrete repairs to the abutments and wing walls upstands, with an in-situ concrete deck infill. The new deck is supported on in-situ reinforced concrete bearing shelves, cast on the existing concrete abutments.

The overall length of the deck is some 9.5m, with a clear span of 7.6m and overall width of 5.85m.

In addition the work also involves waterproofing, steel parapets, surfacing, kerbing, drainage and localised concrete repairs to the abutments and wing walls.

News updates

REPLACEMENT OF OBAN FERRY TERMINAL – LINKSPAN No1

The overall project involves the off-site fabrication and installation of a new linkspan structure at Oban Ferry Terminal for client Caledonian Maritime Assets Ltd (CMal).

12th February 2019

read more

GL return to the Sound of Kerrera

GL making a return visit to the Sound of Kerrera off Oban, to undertake substantial repairs to the breakwater which suffered collision damage following an altercation with a workboat earlier this year.

14th December 2018

read more

Polmadie Bridge official opening……..

Michael Matheson MSP and Cabinet Secretary for Transport, Infrastructure and Connectivity covered all his portfolios at the official opening of the new Polmadie Footbridge giving pedestrian and cycle transport access,

18th September 2018

read more

George Leslie Ltd, Blackbyres Road, Barrhead, Glasgow, G78 1DU  |  mail@georgeleslie.co.uk  |  +44 (0)141 881 9131