George Leslie Ltd
Menu

Key Facts

  • Client: Nustar Grangemouth Ltd
  • Engineer: Stopford Projects Ltd
  • Conditions of contract: Nustar Master Works Agreement
  • Contract value: £3,500,000
  • Duration of works: March 2013 - April 2014

Download the case study

General Civil Engineering, Renewables & Environmental

Nustar Grangemouth Expansion Project

This project was to provide the infrastructure for three new steel fuel storage tanks for Nustar at their existing storage terminal in the port of Grangemouth, and comprised heavily reinforced concrete tank plinth bases constructed on piled foundations with a surrounding concrete containment bund wall.

The main elements of construction included:

  • 750 x 50m long pre-cast concrete piles driven to bedrock.
  • 3 x 30m diam x 1.2m deep heavily reinforced concrete base plinths
  • 300m x 2.5m high reinforced concrete perimeter bund wall
  • Miscellaneous accommodation works including site drainage and service connections

The work was subject to rigorous procedural checks to ensure quality, safety and environmental standards were maintained within this petro-chemical environment with the additional challenge of the live, operational docks location.

Specific features of the construction included:

  • Single 800m3 continuous concrete pours to each base to give a monolithic construction
  • High-spec proprietary waterbar system to bund walls and floor joints
  • Bespoke circular base formwork systems

Extensive programme coordination and liaison was undertaken with follow-on contractors engaged on tank the erection, to open-up work fronts and ensure Nustar production and in-to-service dates were met.

News updates

REPLACEMENT OF OBAN FERRY TERMINAL – LINKSPAN No1

The overall project involves the off-site fabrication and installation of a new linkspan structure at Oban Ferry Terminal for client Caledonian Maritime Assets Ltd (CMal).

12th February 2019

read more

GL return to the Sound of Kerrera

GL making a return visit to the Sound of Kerrera off Oban, to undertake substantial repairs to the breakwater which suffered collision damage following an altercation with a workboat earlier this year.

14th December 2018

read more

Polmadie Bridge official opening……..

Michael Matheson MSP and Cabinet Secretary for Transport, Infrastructure and Connectivity covered all his portfolios at the official opening of the new Polmadie Footbridge giving pedestrian and cycle transport access,

18th September 2018

read more

George Leslie Ltd, Blackbyres Road, Barrhead, Glasgow, G78 1DU  |  mail@georgeleslie.co.uk  |  +44 (0)141 881 9131