George Leslie Ltd
Menu

Key Facts

  • Client: Argyll & Bute Council
  • Engineer: Argyll & Bute Council
  • Conditions of contract: ICE 5th Edition
  • Contract value: £773,000
  • Duration of works: Jan – June 2012 (25 Weeks)

Download the case study

General Civil Engineering, Renewables & Environmental

Milton Burn Culvert, Dunoon

This contract, the 3rd and final phase of the overall Dunoon Flood Prevention Scheme, was to provide an overflow channel in the lower reaches of the Milton Burn which over the years, had been prone to overtopping resulting in severe flooding to the surrounding town centre area.

The major element of the works comprised the construction of approximately 110m of new 3m high reinforced concrete walls and base channel within the lower reaches of the burn, in a constrained location between residential properties and the town’s main supermarket. With a large catchment area from the hillside behind the town and with rapid entry time into the drainage system, the burn was prone to flash flooding with fast-flowing high level flows resulting at short notice. A piled, temporary works solution was installed to contain the flows and enable construction works to progress.

The flows are controlled by the construction of new weir structure within the Milton

Burn together with an inlet chamber and connection to a 1400mm overflow pipeline installed under a previous phase of the scheme.

The project also included the replacement of the existing footbridge over Milton Burn at St Mun`s School with the associated reconfiguration of new footpaths, reconstruction and reinstatement of part of the adjacent supermarket car-park and the removal of extensive invasive Japanese knotweed in the burn area

News updates

GL return to the Sound of Kerrera

GL making a return visit to the Sound of Kerrera off Oban, to undertake substantial repairs to the breakwater which suffered collision damage following an altercation with a workboat earlier this year.

14th December 2018

read more

Polmadie Bridge official opening……..

Michael Matheson MSP and Cabinet Secretary for Transport, Infrastructure and Connectivity covered all his portfolios at the official opening of the new Polmadie Footbridge giving pedestrian and cycle transport access,

18th September 2018

read more

Our Nation’s Tap Water……

GL are ahead of the curve in their support for Scottish Water’s recently launched campaign to encourage people to use a refillable bottle to ‘top up from the tap’ with over 250 GL-branded reusable water bottles distributed across the sites over the past three weeks.

27th June 2018

read more

George Leslie Ltd, Blackbyres Road, Barrhead, Glasgow, G78 1DU  |  mail@georgeleslie.co.uk  |  +44 (0)141 881 9131