Case Studies
Kallin - Pier/Breakwater

The project involved expansion of Kallin Harbour at Grimsay, North Uist in the Outer Hebrides.  The new pier provides this busy fishing harbour with increased berthing capacity and also acts as a breakwater.

During the initial stage of this design and build project, several options were considered for the construction of this deep water facility and following consultation with the local community the best value solution of precast concrete caissons were chosen.

Three identical caissons, each weighing 850t, were constructed in the dry dock at Troon whilst blasting and dredging of 3000m3 of rock was undertaken at the site in preparation for the new pier construction.

The caissons were towed from Troon out to North Uist and carefully lowered onto the prepared seabed at Kallin.  Once secured the caisson walls were completed and the new deck slab constructed.

The main elements of the works included:

  • 3,000m3 of seabed drilled/blasted and dredged
  • 3nr 850t, 20m x 8m x 8.5m precast concrete caissons, constructed at Troon and towed to Kallin
  • 350m2 of pier extension, with 18m x 10m high interlocking precast concrete panels to form the new quay face
  • 5,000m3 of rock filling
  • 1,000m3 of rock armour
  • 500m3 of structural concrete to lift the caisson walls to their final height and provide the pier deck
  • mooring rings, bollards and ladders deck furniture
  • installation of electrical and water services 

Key Facts

   
Client: Comhairle nan Eilean Siar
Engineer: Arch Henderson LLP
Contract Value: £3.85M
Duration of works: July 2007 - July 2008