Roughmute New Recycling Centre

The works are located adjacent to the existing Roughmute Waste Transfer Station on the A883 Glasgow Road near Bonnybridge and involved the construction of a new recycling and waste transfer station the main elements of which were:

  • The excavation and re-use of waste materials deposited and landscaped on site.
  • New blacktop access road and reinforced concrete hardstandings.
  • A  new drainage system including oil interceptor
  • 20 metre high floodlighting, ancillary crash barriers and soft landscaping

Extensive use was made of recycled waste materials:

  • Processed hardcore was used for the capping make-up layer below both the road and concrete hardstandings.
  • Type 1 sub base was produced from processed, recycled waste.
  • A clean 40mm drainage “topsoil” layer incorporating a high percentage of composted green waste was produced from hardcore screenings

Silts were removed from the surface water run-off system by the construction of swales.

 

Key Facts

   
Client: Falkirk Council
Engineer: Jacobs Babtie
Contract Value: £332,000
Duration of works: November 2004 – February 2005